Steps (3) arrow_drop_up arrow_drop_down
Obtain factory drawings approval  (3) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions involved 2 expand_more expand_less

Occupational safety and health authority (x 2)
National Microfinance Bank (NMB)

Results 1 expand_more expand_less

Drawings approval letter

Required Documents expand_more expand_less

Premise Drawings
NMB Bank slip
OSHA Government Receipt

Estimated cost TZS  600,000

expand_more expand_less

USD expand_more expand_less
  • USD Add Name Here
TZS 300,000
par hour par drawing
TZS 300,000
Cost of scrutinizing drawings per hour per drawing

Total Duration 1 d - 16 d expand_more expand_less

  min max
Total time (sum): 1 d 16 d
of which:
Waiting time in queue (sum): 10mn 25mn
Attention at counter: 5mn 1h. 10mn
Waiting time until next step (sum): 0 d 15 d

Laws 3 expand_more expand_less

OSHA ACT 2003 OSHA ACT no. 5 of 2003
  Article S. 21
OSHA client service charter OSHA client service charter
OSHA General Administrative (Amendmend) Rules 2018 OSHA General Administrative (Amendmend) Rules 2018
  Article First schedule